Project Timeline
(subject to change)
-
MAY 2023 - SEPTEMBER 2023
Neighborhood Association Meetings
"Living Room" Meetings
Website Comments
One-on-One Meetings
Informal Surveys
-
SEPTEMBER 2023 - MAY 2024
Panattoni's Commitment(s) to the Community and City of Roseville
"Living Room" Report Out Meeting(s)
Community Open House(s)
-
MAY 2024 - 2027
Project Application Submittal — Completed
City of Roseville Deems Application Complete — Completed
City of Roseville Notice of Preparation of an Environmental Impact Report — Completed
Initial Draft EIR Released for 45-Day Public Review — February 3, 2026 – Completed
Draft EIR Public Comment Opportunity at Planning Commission Meeting — March 12, 2026 – Completed
Initial Draft EIR Public Comment Period Ends — March 23, 2026 – Completed
Project Refinements and Draft EIR Revisions — Spring/Summer 2026
City Recirculates Revised Draft EIR for Public Review — Fall 2026
New Public Review and Comment Period — Fall 2026
Recirculated Draft EIR Public Comment Period Ends — Fall/Winter 2026
City Reviews Comments and Prepares Responses
City Prepares Final EIR
Planning Commission Consideration and Recommendation
City Council Consideration of Project and Final EIR — Anticipated 2027
-
2026/2027